Progress

Progress

 

 

 

 

To view timelapse photos since The Big Build construction project began, click here.

 

February 2009

  • Excavation has been completed on the landside terminal building basement and tug tunnel. Concrete reinforcement and placement is underway.
  • Initial phases of the airside aircraft movement area have been completed to allow for traffic to move around the site; this will allow for construction of the airside concourse.
  • Improvements to the Interim International Arrivals Building are nearing completion and will open for operation February 19, 2009.

October 2008

  • Airside Concourse Construction on schedule to begin February 2009
  • Taxiway W completed
  • Hotel demolition complete
  • New traffic signal installed to facilitate truck traffic
  • Parking lot pavement demolished in preparation for Central Terminal B basement construction